Call for a Free Consultation (360) 891-5811

Search
Close this search box.

Digital Dryshack #95: P6 Status Physical % Complete

We were providing P6 training for Government Contracts at AGC San Diego, a first-class contractor and apprenticeship training facility, when we were surprised by a P6 undocumented feature. Here’s what we discovered:

  • checking ‘Use Steps to Calculate Percent Complete’ , a required setting for D.O.D. schedules, disables updating status when not using steps. (Which is the majority of the time.)
  • therefore we strongly recommend UN-checking the ‘use steps’ checkbox.

The sequence for correctly updating all Activities started but not finished (using Physical Percent Complete) follows:

  1. Check the box for Started and enter current the % Complete
  2. Manually enter Remaining Duration (this prefills the calculated Labor Resource Units and therefore cost to date)
  3. check and modify the Labor Units or % Complete if  required. (this will not affect the Remaining Duration just entered).

This simple workflow restores full autonomy to updating all 3 values exactly as desired, with the added advantage of automatically calculating the costs by entering Remaining Duration.

 

Related posts

Estimating Controls

Does this sound familiar at your company? 1. Bids are time‐consuming 2. Job costing is tedious 3. We’re too busy to change now‐ and besides

Read More »